FINAL ROUTE DEVELOPMENT PLAN:

Technical Memorandum #1: Public Involvement (69-page, 6.3 mb pdf) - Summary of Plan's purpose, involvement of the CWG (Corridor Working Group) members, and other backgroun.
Technical Memorandum #2: Existing Conditions on Corridor (9.4 mb pdf)
Technical Memorandum #3: Traffic Forecasts for Corridor(5.7 mb pdf)
Technical Memorandum #4
: Origin & Destination Study performed for the Monroe Bypass (5.1 mb pdf)

Technical Memorandum #5
(See "Costs" below): Planning Level Project Cost Estimates
Technical Memorandum #6: Environmental Screening along study corridor (6.6 mb pdf)

COSTS (Planning-Level estimates only)

  • Costs per Project:

    SEGMENT #1: MP 3.5 to 12.70 - Approx. Bickford Ave./US 2 Intersection in Snohomish to Monroe's western limit

    Project #1: MP 3.5-12.7 Install median rumble strip, widen shoulder ($18 M)
    Project #2: Corridor-wide improvements: MP3.5 - 56.76 install ITS Traveler infromation (CCTV,VMS) ($4.55 M)
    Project #3: MP 12.46 Dairy Farm (now a rock/gravel business) Channelization and safety improvements (near Monroe's western city limits) ($1.9 M)
    Project #34: MP 3.85 - Add WB pvercrosing [sic; typo; must be "overcrossing." This is the Bickford intersection in Snohomish] and modify EB on ramp ($61.4 M)
    Project #35
    : MP 5.04 @ SR 9 Interchange in Snohomish; add EB lane, new ramp connectors, traffic signals and illumination ($71.7 M)
    Project #46: MP 3.5-12.7 - Widen to four lanes ($257. M)
    Project #46: (This is not a duplicate of Project 46 shown above - 18 ft. median) MP 3.5 to 12.7 - Widen to four lanes ($310 M)
    Project #47: MP 8.51 88th St Interchange - add EB lane, new ramp connectors ($66.9 M)
    Project #48: MP10.08 Westwick Road; realign intersection, add lanes, consolidate driveways ($2.9 M)
    Project #49: MP 10.55 Roosevelt Road, Realign the intersection, add one lane for each direction ($2.0 M)

     

    SEGMENT #2: MP 12.70 to 15.64 - City of Monroe

    Project #4: Add a second SB left turn land on Chain Lake Rd at US 2 and Date of Cost Index: 2006 EB WB right turn only on US2 ($3.0 M)
    Project #5: MP 15.15 Anne/Woods Cr. Rd. - Double left turn ($4.3 M)
    Project #36: MP 12.7-5.6 - Sidewalk improvements [through city of Monroe] ($4.5 M)
    Project Nos. 50 & 51: Monroe Bypass (RTID funding)
    Project #53: MP 12.7-14.57 - add Wb lane, Kelsey through 179th Ave. (Monroe) ($3.9 M)

    Project #54:
    MP12.7-15.64 - Add one lane in each direction ($23 M)

    SEGMENT #3: MP 15.64 to 30.28 - Monroe's eastern city limits through the city of Gold Bar

    Project #6: MP 3.5 - 12.7 Install median rumble strip ($1.4 M)
    Project #7: MP 17.91 WB left turn and EB right turn ($1.84 M)
    Project #8: MP 18.3 EB left turn lane ($1.8 M)
    Project #9: MP 18.98 Construct WB left turn and EB right turn lane (2.04 M)
    Project #10: MP 20.10-20.15 Add left turn and right turn lanes ($3.0 M)
    Project #11: MP 20.7-21.4 Install WB passing lane ($3.2 M)
    Project #12: MP 20.45 Eliminate wide turn-out area ($0.3 M)
    Project #13: MP 22.24-22.93 Additional WB lane, restrict left turn access ($3.2 M)
    Project #14: MP 24.73 Install left turn lane, widen shoulder, or restrict left turn access ($1.6 M)
    Project #15: MP 27 Add EB left turn lane ($1.3 M)
    Project #16: MP 27.45 Install left turn lane ($1.5 M)
    Project #17: MP 28.59-28.9 Extend 2-way left turn lane to 17th street ($3.0 M)
    Project #18: MP 29.48 - Create roundabout ($1.46 M)
    Project #19: MP 30.04 Reiter Rd. Add WB right turn lane ($2.1 M)
    Project #37
    :
    MP 15.6 to 30.28 rural area only widen shoulders, rumble strip, misc. ($23.1 M)
    Project #38: MP 21.42-24.44 Sultan (Additional WB lane) ($9.3 M)
    Project #39: MP 27.51-28.72 Gold Bar (short term) add WB lane, median, Include Roundabout cost ($21.4 M)
    Project #40: MP 27.51-28.72 Gold Bar (add EB lane through Gold Bar ($21.8 M)
    Project #41
    : MP 30.3-50.00 - Widen shoulders, install rumble strip. [Listed as Segment 3, but it includes Segment 4 as well.]
    Project #55: MP 15.6-30.1 - Widen to four lanes ($189.3 M)
    Project #56: MP 21.42-24.44 - Sultan, four lanes, includes roundabouts at 3rd, 5th and 8th Streets ($116.7 M)

    SEGMENT #4: MP 30.28 - 50.00 - East of Gold Bar to just east of the Town of Skykomish

    Project #20: MP 30.3-50.00 - Install median rumble strip (Includes small easternmost portion of Segment 3 and all of Segment 4. ($2.5 M)
    Project #21: MP 30.6 - Intersection improvements in east Gold Bar ($1.0 M)
    Project #22: MP 31.26 - 31.73 - Add left turn lane for Rinker's gravel pit driveway ($1.7 M)
    Project #23: MP 32.23-32.96 - Remark passing lane ($0.3 M)
    Project #24: MP 35.1-35.62 Realign and widen EB and WB bridge approaches ($6.3 M)
    Project #25: MP 35.45-35.55 - Install chevron warning signs ($80,000)
    Project #26: MP35.35-35.62 - Eliminate driveway access, install edge rumble strip ($1.6 M)
    Project #27: MP 35.95-36.4 - Construct EB truck climbing lane ($2.3 M)
    Project #28: MP 38.5 - Reslope shoulder ($1.3 M)
    Project #29: MP 45.9 - Add WB left turn lane ($2.0 M)
    Project #30: MP 48.7-49.5 - Pedestrian improvement ($4.5 M)
    Project #31: MP 49.51 - Add WB left turn lane ($1.4 M)
    Project #32: MP 49.98 - Old Cascade Hwy, add WB left turn lane ($2.6 M)
    Project #33: MP 49.8-50.2 - Add 2 way left turn lane ($1.9 M)
    Project #43: MP 35.62 -Index-Galena Road, add WB right turn lane ($3.9 M)
    Project #44: MP 41-43 - Widen to four lanes ($33.9 M)
    Project #45: MP 48.71 5th Street - Skyhomish Roundabout ($5.4 M)

    Note: At this point the Project numbers do not flow in an unbroken numerical sequence.

    Project #34: See Segment #1
    Project #35: See Segment #1
    Project #36: See Segment #2
    Project #37: See Segment #3
    Project #38: See Segment #3
    Project #39: See Segment #3
    Project #40: See Segment #3
    Project #41: See Segment #3
    Project #42: Corridor-Wide Project - MP 3.5 - 50.0 Widen or replace 26 bridges ($75.2 M)
    Project #43: See Segment #4
    Project #44: See Segment #4
    Project #45: See Segment #4
    Project #46 (Two #46 projects are detailed): See Segment #1
    Project #47: See Segment #1
    Project #48: See Segment #1
    Project #49: See Segment #1
    Project #50 & Project #51: MONROE BYPASS (RTID funding)
    Project #52: Corridor-Wide Project (Same info/costing as Project #42)
    Project #53: See Segment #2
    Project #54: See Segment #2
    Project #55: See Segment #3
    Project #56: See Segment #3

 

 

 

 

 

Links to
RDP-related issues

DEFINITION OF ABBREVIATIONS USED IN THE COST ESIMATES:

MP = "Mile Post"

SB, NB, EB, WB (means "Southbound, Northbound, Eastbound and Westbound," respectively)

A glossary of all terms used in the RDP can be found within the first few pages of the Plan.

 

 

 
   

Home

Calendar & Events

Documents
Meeting Minutes & Audio
News & Info
Make a difference
Legislative Issues
Donations
Links
Who we are

Contact us: via email or snail mail at P.O.Box 1829, Sultan, WA 98294